Tracing Activities

 
Tracing Activities
1

Trace Up

1. Trace Up
Traces all the activities leading up to the selected activity i.e, it traces all the predecessors of the selected activity AND hides all the other tasks in the view.
2

Trace Down

2. Trace Down
Traces all the activities following/succeeding the selected activity i.e, it traces all the successors of the selected activity AND hides all the other tasks in the view.
3

Trace Bidirectional

3. Trace Bidirectional
Traces all the activities leading up to AND following/succeeding the selected activity i.e, it traces all the predecessors AND the successors of the selected activity, AND hides all the other tasks in the view.
4

Custom Trace

4. Custom Trace
Let's the user run a custom trace of the selected activity by specifying the Nest Level. The user has the freedom to choose the direction and select either the filter or select actions.
5

Trace Up Keep Current

5. Trace Up Keep Current
Traces all the activities leading up to the selected activity i.e, it traces all the predecessors of the selected activity AND keeps all the other tasks in the current view.
6

Trace Down Keep Current

6. Trace Down Keep Current
Traces all the activities following/succeeding the selected activity i.e, it traces all the successors of the selected activity AND keeps all the other tasks in the current view.
7

Trace Bidirectional Keep Current

7. Trace Bidirectional Keep Current
Traces all the activities leading up to AND following/succeeding the selected activity i.e, it traces all the predecessors AND the successors of the selected activity, AND keeps all the other tasks in the current view.