plan better with vPlanner
 
×

Importing MS Project XML Files

 
Please follow the Import Manager standard process to import activities from MS Project XML. 
 

Notes

  • vPlanner will map the WBS codes to the User 01 field in vPlanner.
  • MS Project does not have a concept of Global task IDs.  vPlanner uses the UID field when importing tasks from MS Project.  However, there is no guarantee that UIDs will be unique if you import from different MS project files.