When moving a task or a selection of tasks, bends will now auto clear so that the associated logic ties move with the task or tasks.
Export vPlanner XML now includes both predecessor IDs and successor IDs in the export.
The Gantt View report now includes Company Names in the table side of the report.
It is not possible to configure the printed page to allow Top-Left placement of the tasks. Prior to this release Center was the only option.
Improved Features
Improved the visibility of Dotted lines for resource constraints when displayed on high-dpi monitors.
Show composite task description is no longer the default option in timeline view.
Fixes
Fixed an issue that prevented passwords resets from going out when using the password reset option under the attributes menu.
Fixed an issue that prevented newly created split tasks from being copies using Copy/Paste.
Resources now export/import as expected in the vPlanner XML export.
Tasks with few words will now scale better in printed views. Prior behavior was limited to 1.5 times of defined text size. New setting is 3 times the original font size.
Gantt report will now calculate the correct FF date for the summary bars.
Known Issues
Shortcuts for User fields in the attribute editor are limited to a total of 128 characters for all pre-set options combined. Try to keep options descriptions short if you need more options.