New Features
-
When moving a task or a selection of tasks, bends will now auto clear so that the associated logic ties move with the task or tasks.
-
Export vPlanner XML now includes both predecessor IDs and successor IDs in the export.
-
The Gantt View report now includes Company Names in the table side of the report.
-
It is not possible to configure the printed page to allow Top-Left placement of the tasks. Prior to this release Center was the only option.
Improved Features
-
Improved the visibility of Dotted lines for resource constraints when displayed on high-dpi monitors.
-
Show composite task description is no longer the default option in timeline view.
Fixes
-
Fixed an issue that prevented passwords resets from going out when using the password reset option under the attributes menu.
-
Fixed an issue that prevented newly created split tasks from being copies using Copy/Paste.
-
Resources now export/import as expected in the vPlanner XML export.
-
Tasks with few words will now scale better in printed views. Prior behavior was limited to 1.5 times of defined text size. New setting is 3 times the original font size.
-
Gantt report will now calculate the correct FF date for the summary bars.
Known Issues
-
Shortcuts for User fields in the attribute editor are limited to a total of 128 characters for all pre-set options combined. Try to keep options descriptions short if you need more options.
|